Project Update: Heritage Bank

Our team has been working hard on the Heritage Bank – Northfield location. The landscaping and sodding will be done this week, with the final coat of blacktop being done on Friday. Next week the final metal finishes on the exterior of the building will be completed. This week, on the interior, we have cabinets and casework along with wood trim and flooring going down. Kitchen equipment and bank equipment will be arriving in early November. We are expecting the project to be wrapping up closer to November 22.