St. Pius V Catholic Church elevator

We have been making good progress on the addition to St. Pius V Catholic church in Cannon Falls. The addition will house a new elevator as well as a fully accessible toilet. It is always slow coming out of the ground with an elevator as you have to dig and prepare the pit for the shaft as part of the excavation work. The foundation walls are in place now. Our workers have set the main floor steel beams in place as well as the steel decking that supports the concrete floor. Yesterday we got underway with the main floor concrete block walls.